    A signed a contract for building a road of 1920 meters long within 120 days. He employed 160 workers for this task. But after 24 days he found that only 1/8 of the task has been finished. If A want to finish the road in time how many additional workers he has to employee ?

    ক)
    180
    খ)
    120
    গ)
    160
    ঘ)
    280

    Explanation

    Solution: Days remaining = 120 - 24 = 96 Work done = 1920/8 = 240 meter and work remaining = 1920 - 240 = 1680 meter 240 meter is done in 24 days by = 160 men 1   "        "     "    "   1  "      "    = (160 × \times 24) / 240 men. 1680  "         "     "   "   96 "      "     = (160 × \times 24 × \times 1680) / 240 × \times 96  men = 280 men Additional men need = 280 - 160 = 120 Men.